In short: Small contractors most often meet DCAA through a pre-award accounting system audit, a floor check of timekeeping, a proposal or rate review, and an audit of their incurred cost submission. Each one tests the same thing: can your records show what you spent, on which contract, and why it is allowable?

From the Peter Witts CPA PC team, led by a former DCAA auditor · November 2026

The audits, in the order most companies meet them

Audit When it happens What the auditor asks
Pre-award accounting system Before a first cost-type award, such as many DoD Phase II SBIRs Can your system separate and track costs by contract?
Proposal or rate review When you price a cost-type proposal Are your rates and estimates supported by your books?
Floor check During performance, often unannounced Do employees record time daily, to the right project?
Incurred cost audit After year-end submissions Were the costs you billed allowable and allocated correctly?
Billing or voucher review Ongoing on cost-type contracts Do invoices tie to the ledger and the contract terms?

What we see from the auditor's side

Most findings are not about fraud. They come from small habits: timesheets filled in at the end of the week, unallowable costs mixed into overhead, or invoices built from a spreadsheet that does not match the ledger. Fixing those habits early is far cheaper than explaining them later.

A 10-point readiness checklist

  • Chart of accounts separates direct, indirect and unallowable costs
  • Every cost is coded to a contract or an indirect pool
  • Employees record time daily, with changes approved and explained
  • Labor distribution ties timesheets to payroll
  • Indirect rates are calculated monthly, not just at year-end
  • Unallowable costs are identified and excluded from billings
  • Invoices reconcile to the general ledger
  • Written accounting policies match what you actually do
  • Subcontract and consultant costs have agreements and approvals on file
  • Someone other than the bookkeeper reviews month-end close

FAQ

Will DCAA audit a firm-fixed-price contract? Usually not for costs, though pricing and pre-award reviews can still apply.

Can a floor check really be unannounced? Yes. That is why daily timekeeping matters more than any other single habit.

Who requests a DCAA audit? The contracting officer, not the contractor.

Want to know how you would do today? We run a mock review against this list before an auditor does. Request a consultation.